Highway Repairs Coming to Slave Lake Region

Details Repairs

Earlier today, We released a letter from Minister McIver about the Highway repairs coming to Slave Lake 

A timeline of the work is below

-       Signals at Highway 2/Highway 88 to be started this year

-       Highway 2 paving is for 2020 start and expecting to continue into 2021. 

Here is a detailed look on what is planned to be repaired:

  • Highway 2 Paving Project

4.2 km south of Highway 88
10 km north of Highway 88
11 km near Canyon Creek

  • Traffic Signals at intersection of Highway 2 and Highway 88

Highway 2 Paving Projects:

Screen Shot 2020-05-20 at 1.14.46 PM


  • Highway 88 Bridges – Lily Creek and Brady Creek
    • Tender is advertised as of May 19, 2020
    • Tender closing date is June 10, 2020
  • Breakout Repair Work Planned:
    • 4 patches to the west of town
    • 9 patches to the east (including around Main St and the Highway 88 junction)
    • 3 patches up on Highway 88 and a few up on 754
  • Continued Pothole patching as required
    • Typical Patching Quantities:
      • Five Year Average: 61,400 kg
      • to date 121,500 kg

Facebook Twitter Email

Other News in News and Updates

Library Reopening Today

Slave Lake Library Reopened Today

Posted on: July 13, 2020
Coronavirus Update

COVID-19 Updates

Posted on: March 15, 2020
Submit A VLOG Question Today

Your Questions For Slave Lake VLOGS

Posted on: January 22, 2019
Advertise on the Electronic Sign

Advertise on the Digital Signs Today!

Posted on: January 9, 2019
Traffic Analysis Website

Traffic Analysis Site

Posted on: October 12, 2018